Restrict By Lockview.

Our Categories

Contact Us

Tel: +86-543-3611555

Fax:+86-543-3615999

Email:info@ultrasonicscn.com

skype:longruncn

24 hours service

+86-186-5435-6933

Heat meter installation requirements

1.Selection of fluid filled material uniform and dense, ease of the ultrasonic output tube segments, such as vertical pipe section ( the upward flow of the fluid ) or horizontal pipes.
2.Installation distance should be greater than 10 times the diameter of the upper straight pipe, pipe diameter less than downstream is greater than 5 times without any valve, elbow, reducer, uniform and straight pipe section, the installation point should be sufficiently far away from the valve, pump, high voltage and inverter interference source.
3.Avoid installed in the pipeline of the highest point of the system or with a free outlet vertical pipeline ( downward movement of the fluid ).
4.Mount point temperature, pressure sensor can work in the range of.
5.Give full consideration to the inner wall of the tube scaling status; try to choose no scaling pipeline installation, such as can not be met, the scaling considerations for lining in order to better precision of measurement.